Steel, Sand, and Sovereignty: Navigating Construction Contracts Amidst the 2026 Gulf Conflict
- Adebowale Oyinleye
- 1 day ago
- 8 min read

Introduction: Infrastructure Under Geopolitical Stress
Infrastructure development in the Gulf Cooperation Council (GCC) has historically operated within a complex interplay of geopolitics, energy economics, and global supply chains. Yet the 2026 escalation involving Iran, the GCC states, the United States, and Israel has introduced a new and acute level of contractual uncertainty. The geopolitical landscape has shifted from the "just-in-time" efficiency of the early 2020s to a "just-in-case" survivalist framework.
The Strait of Hormuz, through which approximately 20–22% of the world’s seaborne oil and a significant proportion of construction materials transit, has become a strategic chokepoint. Disruptions to maritime shipping, heightened naval patrols, and war-risk exclusions by insurers have already begun to ripple through steel supply chains, aluminium extrusion markets, and specialised plant procurement.
For construction projects in the United Arab Emirates and Saudi Arabia, these developments do not remain abstract geopolitical events—they manifest directly as:
Delayed delivery of structural steel and mechanical plant.
Rapid escalation of war-risk insurance premiums.
Increased security protocols at project sites due to missile and drone threats.
Shipping reroutes that extend lead times by weeks or months.
Under international construction contracts—particularly the FIDIC Red Book 1999 and the FIDIC Conditions of Contract 2017—these events raise critical questions:
Do such disruptions constitute Force Majeure or Exceptional Events?
Are contractors entitled to Extension of Time (EOT) only, or both time and cost?
At what point does performance become legally impossible, triggering contractual release?
From the vantage point of a contract administrator, the answers lie in a careful reading of contractual risk allocation, the governing civil law framework of the GCC, and lessons learned during the COVID-19 pandemic disruption.
I. Strategic Supply Chain Disruption: The Strait of Hormuz Effect
The Strait of Hormuz is the maritime artery connecting Gulf ports to global trade. For the GCC construction sector, its disruption creates cascading consequences:
a. Steel and Structural Components
Structural steel used in major Gulf infrastructure projects is sourced from:
China
India
Turkey
South Korea
European mills
With shipping insurers applying war-risk surcharges, freight rates have surged dramatically. In some cases:
Typical steel delivery schedules could shift from 6–8 weeks to 10–15 weeks depending on the interplay between insurance premiums and change of shipping route.
Letters of credit now require additional security provisions.
Suppliers demand price escalation clauses to offset volatility.
b. Aluminium and Facade Systems
The Gulf façade industry relies heavily on specialised aluminium extrusion dies and coatings sourced internationally. Maritime delays affect:
Curtain wall systems
Architectural aluminium profiles
Structural glazing assemblies
For high-rise developments in Dubai, Riyadh, and NEOM, these components may sit on the critical path of project programmes.
c. Specialised Plant and Equipment
Major projects depend on imported machinery such as:
Tunnel boring machines
HVAC chillers
Turbine equipment
Electrical transformers
Shipping reroutes around the Cape of Good Hope instead of the Gulf passage can add weeks to transit times.
In contractual terms, such delays immediately raise questions under FIDIC Force Majeure / Exceptional Event provisions.
II. Employer’s Risks: War, Hostilities, and Invasion
Under the FIDIC Red Book 1999, risk allocation relating to armed conflict is primarily addressed in Sub-Clause 17.3 and 17.4.
Sub-Clause 17.3 – Employer’s Risks
Employer’s risks include damage resulting from:
War
Hostilities
Invasion
Act of foreign enemies
Rebellion or revolution
In GCC arbitration practice, the significance of this clause cannot be overstated.
If project disruption results from regional military activity, liability for physical damage to the works typically rests with the Employer, not the contractor.
Examples include:
Missile interception debris damaging site structures
Shockwave damage to glazing systems
Drone strike incidents near infrastructure facilities
Sub-Clause 17.4 – Consequences
Where Employer’s Risks materialise, the contractor is generally entitled to:
Extension of Time
Payment of Cost
This differs markedly from other Force Majeure scenarios where cost recovery may be restricted.
In arbitration, the key evidentiary question becomes causation:
Did the war event directly cause the delay or damage?
If so, the contractor’s entitlement becomes relatively strong.
III. Force Majeure vs Exceptional Events
The FIDIC 1999 and FIDIC 2017 editions approach extraordinary disruptions differently.
FIDIC 1999 – Sub-Clause 19.1: Force Majeure
Force Majeure must satisfy four conditions:
Beyond the party’s control
Unforeseeable
Unavoidable
Not attributable to either party
The current Gulf conflict arguably satisfies all four.
Beyond Control
Contractors cannot control geopolitical conflict or maritime security restrictions.
Unforeseeable
While geopolitical tensions have long existed, armed escalation disrupting the Strait of Hormuz constitutes a material escalation beyond ordinary risk.
Unavoidable
Even alternative logistics routes may be blocked by insurance restrictions or naval security protocols.
Not Attributable
Neither employer nor contractor can reasonably be held responsible for regional military conflict.
Thus, under Sub-Clause 19.1, the conflict would typically qualify as Force Majeure.
FIDIC 2017 – Sub-Clause 18.1: Exceptional Events
The 2017 suite replaced the term Force Majeure with Exceptional Events.
This change reflects modern legal drafting trends, emphasising precise risk allocation.
Examples explicitly listed include:
War
Hostilities
Terrorism
Military operations
Accordingly, the current Gulf conflict fits squarely within the contractual definition.
IV. Consequences: Extension of Time vs Cost
Under both FIDIC editions, consequences depend on the nature of the event.
Sub-Clause 19.4 (1999) / 18.4 (2017)
Contractors affected by Force Majeure or Exceptional Events may claim:
Extension of Time (EOT)
Cost, but only for certain categories of events.
Critically:
Event Type | EOT | Cost |
War / Hostilities | Yes | Yes |
Natural disasters | Yes | Often No |
Government actions | Case dependent | Case dependent |
This distinction is fundamental in GCC disputes.
For instance:
A typhoon disrupting shipping might grant EOT only. But naval conflict closing shipping routes could justify EOT plus cost. Cost claims may include:
Standby labour
Equipment idle costs
Re-mobilisation
Escalated material prices
V. Release from Performance: When Contracts Become Impossible
In extreme circumstances, the contract may become impossible to perform.
Under Sub-Clause 19.7 (1999) or 18.6 (2017), either party may terminate if:
The Force Majeure prevents performance for a prolonged period.
Continued execution becomes impossible or unlawful.
This interacts directly with GCC civil law doctrines.
UAE Civil Code – Article 273
Article 273 provides that if force majeure renders performance impossible, the corresponding obligation is extinguished.
This reflects the civil law doctrine of frustration of purpose.
Saudi Civil Transactions Law
Similarly, Saudi law recognises:
Impossibility
Excessive hardship
Where war conditions make construction illegal or physically impossible, the contract may be dissolved. However, arbitrators typically apply a high threshold before declaring impossibility. Logistical difficulty alone rarely suffices.
VI. Physical Security Risks to Construction Sites
The 2026 conflict introduces a dimension rarely contemplated in ordinary construction risk planning: direct military threats to project sites.
Potential impacts include:
1. Mandatory Security Protocols
Authorities in the UAE and Saudi Arabia may impose:
Radar monitoring zones
Evacuation drills
Work stoppages during threat alerts
Such directives could trigger claims under:
Variation
Change in Law
Exceptional Event
2. Temporary Site Shutdowns
Air defence engagements near infrastructure corridors may require:
Evacuation of personnel
Shutdown of cranes and tower lifts
Suspension of concrete pours
These disruptions are typically classified as prevention, not merely hindrance.
VII. The COVID-19 Corollary
The construction industry gained profound contractual experience during the 2020–2022 pandemic.
Yet the current conflict differs in important ways.
Prevention vs Hindrance
During COVID-19:
Many projects continued operating under restrictions.
Courts often viewed the pandemic as hindrance, not impossibility.
In contrast, wartime disruptions may create true prevention, where:
Shipping lanes close completely.
Government orders halt construction activity.
Prevention strengthens claims for Force Majeure relief.
Data-Driven Claims: Lessons from Pandemic Disputes
COVID-era arbitration established a critical lesson:
Claims succeed only when supported by granular contemporaneous data.
Contractors learned to track:
Labour productivity losses
Logistics delays
Supply chain disruptions
These same protocols must now be applied to wartime impacts.
Essential documentation includes:
Shipping notices
Insurance premium increases
supplier delay notices
revised logistics routes
programme impact analyses
Without such data, Force Majeure claims risk failure.
VIII. Governing Law and Lex Loci Solutionis
Another critical legal concept in international arbitration is lex loci solutionis—the law of the place where contractual obligations are performed.
In GCC infrastructure contracts:
Governing law may be UAE law, Saudi law, or occasionally English law.
However, mandatory local laws still influence performance.
For instance:
If the UAE government orders a temporary shutdown of coastal industrial zones, contractors cannot legally continue work.
This creates a strong argument for:
Exceptional Event relief
Potential contract suspension
IX. Quantum Meruit and Post-Termination Compensation
If contracts terminate due to impossibility, the question arises:
How are contractors compensated?
FIDIC typically allows recovery for:
Work executed
Demobilisation costs
removal of equipment
materials ordered but unused
This recovery resembles the legal principle of quantum meruit—payment for the value of work performed. However, profit on unexecuted work is rarely recoverable.
X. Boardroom Imperatives for Navigating Wartime Risk
In light of the evolving Gulf conflict, project stakeholders should adopt several strategic measures.
1. Strict Compliance with Notice Requirements
The "Notice" Trap: Under FIDIC 2017, the 28-day notice period for an "Exceptional Event" is a condition precedent. Failure to notify the Engineer within this window can result in a total loss of claim rights.
Under FIDIC:
Notice must typically be issued within 28 days of becoming aware of the event.
Failure to provide timely notice can bar claims entirely.
2. Implement Wartime Supply Chain Monitoring
Contractors should establish real-time monitoring of:
Shipping routes
supplier manufacturing schedules
war-risk insurance premiums
This data supports disruption claims.
Mitigation of Loss: Even in a war zone, the Contractor has a duty to mitigate. Can materials be sourced via the Red Sea or overland through Jordan/Saudi? If a "reasonable" alternative exists, the FM claim may fail.
3. Reassess Insurance Coverage
· Conduct an insurance Gap Analysis: Review your Construction All Risks (CAR) policy. Most exclude "War" but may cover "Terrorism" or "Riot." The distinction in 2026 is often blurred; legal definitions will determine who pays for site damage.
· Projects must review:
War-risk exclusions
marine cargo coverage
delay in start-up insurance
Failure to update coverage may expose parties to significant uninsured losses.
4. Invoke Hardship (Imprévision) Where Appropriate
Many GCC civil law systems recognise the doctrine of imprévision (French law (Art. 1195 Civil Code), which allows courts or arbitral tribunals to rebalance contracts where circumstances become excessively onerous.
This doctrine may allow:
price adjustments
contract renegotiation
without terminating the project.
5. Consider Contractual Renegotiation
Finally, the most commercially sensible solution may be proactive renegotiation.
Parties should consider:
material escalation mechanisms
shared risk logistics solutions
revised programme milestones
Litigation rarely preserves project relationships.
6. Termination for Prolonged FM:
If the conflict prevents work for a continuous period of 84 days (under FIDIC Sub-Clause 19.6), either party may terminate. This is the "Nuclear Option" that requires a deep cost-benefit analysis of the "Termination Amount."
Conclusion: Contractual Resilience in an Uncertain Gulf
The 2026 Gulf conflict underscores a perennial truth in international construction law:
Infrastructure does not exist in isolation from geopolitics. The disruption of the Strait of Hormuz, escalation of war-risk insurance, and emerging physical threats to project sites create a complex matrix of contractual risks.
Within the FIDIC framework, these events generally qualify as Force Majeure or Exceptional Events, potentially entitling contractors to both Extension of Time and Cost—particularly where war or hostilities are involved.
Yet successful claims will depend not merely on legal doctrine, but on:
meticulous documentation
timely notices
strategic risk management
Ultimately, the most resilient projects will be those where parties recognise that steel and sand are inseparable from sovereignty, and where contracts are interpreted not only through clauses and statutes, but through the realities of a rapidly evolving geopolitical landscape.




Comments